BACK TO PROJECTS

9th September 2025

Thor OWF

Jan De Nul – Thor OWF – August 2025 to Present – Termination & Testing of 66kV inter- cables – 72 WTGs, 16 Strings, 1 OSS

SPIE Wind Connect was awarded the contract by Jan De Nul, a global leader in maritime construction. The project is to complete the 66kV (IAC) termination and testing on 72 wind turbine generators for RWE’s Thor Offshore Wind Farm.

These works are due to commence in July 2025 with the mock-up scheduled for November 2024.

Jan De Nul was awarded the EPCI cable contracts by RWE in consortium with Hellenic Cables, and will provide the entire cable package, including the manufacture and installation of 60 kilometres of export cables on the 30-kilometre-long cable route from the offshore wind farm to shore, and approximately 200 kilometres of inter-array cables.

Offshore installation and commissioning of the cable system are expected in 2025.

Scope of work (but not limited to} the following elements:

  • T&T Mock up & OSS Shipyard Site Visit
  • Post Loadout Testing
  • Termination & Testing of the Inter Array Cables on WTG
  • Termination & Testing of the Inter Array Cables on OSS

For further information: Contact Us

More Projects from SPIE Wind Connect

TPC Phase II

Taiwan Power Company (TPC) Phase II Offshore Windfarm – August 2025 to Ongoing Scope: Termination & Testing of 31 66Kv Inter-Array Cables (IACs) and 1 Export Cable SPIE Wind Connect […]

Hollandse Kust West VI OWF

Van Oord – Hollandse Kust West VI OWF – Main Campaign April 2026 – Termination & Testing of 66kV inter- cables – 52 WTGs, 1 OSS SPIE Wind Connect has […]

Windanker OWF

Van Oord – Windanker OWF – Main Campaign Jan 2026 – Termination & Testing of 66kV inter- cables – 21 WTGs, 5 Strings, 1 OSS SPIE Wind Connect was awarded […]

Stylish curve

UVDB Logo BMA Trade Logo