Formosa 2 OWF

Jan De Nul – Formosa 2 Offshore Wind Farm – January 2022 to September 2022 – 66kV Array & Export Cables

Correll Electrical Engineering (CEE) were delighted that Jan De Nul once again chose our company to complete the subsea cable termination & testing works on their 3rd contract Taiwan waters. The Formosa 2 project will be managed through our Taiwan Brach with the HQ in Taipei,  we shall be deploying our two local technicians onto the project throughout.

On the Formosa 2 project, Correll Services was responsible for:

  • Pre-project meetings
  • Site visits
  • Creation of RAMS
  • Mock-up trials at Switchgear and TP manufacturers facilities in Indonesia.
  • Creation of quality documentation
  • Project HIRA meetings
  • Post Lay Testing (continuity, insulation resistance, Time Domain Reflectometry and Optical Time Domain Reflectometry).
  • Onshore export cable stripping and routing
  • Onshore export jointing of the HV & FO cables

On the offshore assets:

  • Stripping the export cables to expose the HV cores and FO cable
  • Stripping the array cables to expose the HV cores and FO cable
  • Complete the permanent hang-off
  • Route the HV and FO cable into the TP/WTGS
  • Cleat the HV cores from the hang-off to the GIS
  • Terminate and splice the FO cable into the cabinet
  • Terminate three power cores into the GIS
  • Complete post installation testing from the onshore substation to the offshore assets (VLF, IR, TDR & OTDR)
  • Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone.

Download

For further information: Contact Us

More Projects from SPIE Wind Connect

TPC Phase II

Taiwan Power Company (TPC) Phase II Offshore Windfarm – August 2025 to Ongoing Scope: Termination & Testing of 31 66Kv Inter-Array Cables (IACs) and 1 Export Cable SPIE Wind Connect […]

Hollandse Kust West VI OWF

Van Oord – Hollandse Kust West VI OWF – Main Campaign April 2026 – Termination & Testing of 66kV inter- cables – 52 WTGs, 1 OSS SPIE Wind Connect has […]

Windanker OWF

Van Oord – Windanker OWF – Main Campaign Jan 2026 – Termination & Testing of 66kV inter- cables – 21 WTGs, 5 Strings, 1 OSS SPIE Wind Connect was awarded […]

Stylish curve

UVDB Logo BMA Trade Logo