Block Island OWF Cable Repair

Global Offshore – Block Island OWF Cable Repair – August 2020 to May 2021 – 1 Export Subsea Cable

Global Offshore approached CS to support them with HV and FO services associated with the Block Island cable repair/replacement project in the USAThis is the second contract for Correll Services in the USA associated to OWF’s cable repairs. We are responsible for the Jointing & Testing of the Export cables between Land and the Wind Turbine Generator, including: 

  • Mobilising 6 Technicians and 1 Offshore Installation Manager 
  • Pre-project meetings 
  • Site visits (jointing habitat)  
  • Creations of RAMS 
  • Creation of quality documentation 
  • Project HIRA meetings 
  • Load-out Testing 
  • Post Lay Testing (continuity, insulation resistance, Time Domain Reflectometry and Optical Time Domain Reflectometry). 
  • On the offshore CLV & assets: 
    • Cutting of existing Export cable 
    • Stripping the Export cables to expose the HV cores and FO cable 
    • Complete the 33kV Power CSL subsea Joint. 

Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone.

Download

For further information: Contact Us

 

More Projects from SPIE Wind Connect

TPC Phase II

Taiwan Power Company (TPC) Phase II Offshore Windfarm – August 2025 to Ongoing Scope: Termination & Testing of 31 66Kv Inter-Array Cables (IACs) and 1 Export Cable SPIE Wind Connect […]

Hollandse Kust West VI OWF

Van Oord – Hollandse Kust West VI OWF – Main Campaign April 2026 – Termination & Testing of 66kV inter- cables – 52 WTGs, 1 OSS SPIE Wind Connect has […]

Windanker OWF

Van Oord – Windanker OWF – Main Campaign Jan 2026 – Termination & Testing of 66kV inter- cables – 21 WTGs, 5 Strings, 1 OSS SPIE Wind Connect was awarded […]

Stylish curve

UVDB Logo BMA Trade Logo