13th January 2023

Acadis OST 1 OWF

Global Marine – Acadis OST 1 – September 2022 to November 2022 – 27 Array Subsea Cables

The Correll Group, Electrical Engineering Division (CEE) have been successful in securing a contract from the Global Marine Group for the post installation integrity testing of all 27 inter-array cables on the Arcadis Ost 1 offshore wind farm.

Arcadis Ost 1 is located in the Baltic Sea, 19 km northeast of the island of Rügen in Germany. Spanning an area of 29 km² and consisting of 27 Vestas V 174 – 9.5 MW wind turbines, Arcadis Ost 1 will have the capacity of 257 MW when fully operational, producing enough green energy to power up to 290,000 households.

The summary of work included:

  • Pre-project meetings
  • Monthly meetings
  • Creations of RAMS
  • Project HIRA meetings
  • Pre Project training
  • Mobilisation of PPE, Cable pulling equipment, tools & test equipment.
  • Pre & Post Lay Testing (Continuity, Insulation Resistance and Optical Time Domain Reflectometry).

Following completion of the offshore phase two spare IACs were offloaded to reels and the following tests were undertaken;

    • Visual inspection.
    • Uni-directional OTDR of 25% of the IAC fibre-optics.
    • TDR measurement of the conductors.
    • IR tests (DC voltage test of the outer sheath of all three cores, in accordance with IEC63026, chapter 13.2).

On the offshore assets:

    • Stripping the array cables to expose HV cores and fibre optical cable.
    • Resealing the cable ends and ensuring the cable is safely stowed before departing site.

More Projects from SPIE Wind Connect

TPC Phase II

Taiwan Power Company (TPC) Phase II Offshore Windfarm – August 2025 to Ongoing Scope: Termination & Testing of 31 66Kv Inter-Array Cables (IACs) and 1 Export Cable SPIE Wind Connect […]

Hollandse Kust West VI OWF

Van Oord – Hollandse Kust West VI OWF – Main Campaign April 2026 – Termination & Testing of 66kV inter- cables – 52 WTGs, 1 OSS SPIE Wind Connect has […]

Windanker OWF

Van Oord – Windanker OWF – Main Campaign Jan 2026 – Termination & Testing of 66kV inter- cables – 21 WTGs, 5 Strings, 1 OSS SPIE Wind Connect was awarded […]

Stylish curve

UVDB Logo BMA Trade Logo