Formosa 2 OWF Cable Repair

Jan De Nul – Formosa 2 OWF Cable Repair – July 2023 to August 2023 – IAC between 2x WTGs

Jan De Nul approached Correll Cable Installation and Power Services Division to support them with the cable pull/replacement on Formosa 2 Offshore Wind Farm.

Correll were responsible for the removal of the damaged IAC between x2 Wind Turbine Generators (WTGs) and the installation, termination and testing of the replacement IAC.

Scope of work included:

  • Mobilising Technicians and Offshore Installation Manager 
  • Pre-project meetings 
  • Creations of RAMS 
  • Creation of quality documentation 
  • Project HIRA meetings 
  • On the offshore assets: 
    • Cutting of existing array cables ready for extraction
    • Cable Pull operation.
    • Stripping the array cables to expose the HV cores and FO cable
    • Complete the permanent hang-off
    • Route the HV and FO cable into the OSS/WTGS
    • Cleat the HV cores from the hang off to the GIS
    • Terminate and splice the FO cable into the cabinet
    • Terminate power cores into the GIS

Download

For further information: Contact Us

More Projects from SPIE Wind Connect

TPC Phase II

Taiwan Power Company (TPC) Phase II Offshore Windfarm – August 2025 to Ongoing Scope: Termination & Testing of 31 66Kv Inter-Array Cables (IACs) and 1 Export Cable SPIE Wind Connect […]

Hollandse Kust West VI OWF

Van Oord – Hollandse Kust West VI OWF – Main Campaign April 2026 – Termination & Testing of 66kV inter- cables – 52 WTGs, 1 OSS SPIE Wind Connect has […]

Windanker OWF

Van Oord – Windanker OWF – Main Campaign Jan 2026 – Termination & Testing of 66kV inter- cables – 21 WTGs, 5 Strings, 1 OSS SPIE Wind Connect was awarded […]

Stylish curve

UVDB Logo BMA Trade Logo