BACK TO PROJECTS

15th March 2021

Centrica Platform 3B

Fabricom Quanta  Centrica Platform 3B – October 2020 to May 2021 – Cable Pulling Platform Cables  

CS were approached to support Quanta them with cable pull in activities of HV & LV cables on the platform between Transformers, Switch Gears etc. CS were responsible for the following,  

  • Pre-project meetings 
  • Site visits  
  • Creations of associated documentation 
  • Project HIRA meetings 
  • Mobilisation of PPE & tools via a 10ft container 
  • On the 2 x offshore platforms assets: 
    • Implement lift and pull plans 
    • OSS mobilisation and preparation 
    • Pull the HV cable to the associated assets  
    • Route the HV/LV cable to the associated assets  
    • Cleat the HV/LV cables to the associated assets 
    • Deliver an Inspection and Test Plan of the installed and tested system, forming part of key payment milestone. 

More Projects from SPIE Wind Connect

TPC Phase II

Taiwan Power Company (TPC) Phase II Offshore Windfarm – August 2025 to Ongoing Scope: Termination & Testing of 31 66Kv Inter-Array Cables (IACs) and 1 Export Cable SPIE Wind Connect […]

Hollandse Kust West VI OWF

Van Oord – Hollandse Kust West VI OWF – Main Campaign April 2026 – Termination & Testing of 66kV inter- cables – 52 WTGs, 1 OSS SPIE Wind Connect has […]

Windanker OWF

Van Oord – Windanker OWF – Main Campaign Jan 2026 – Termination & Testing of 66kV inter- cables – 21 WTGs, 5 Strings, 1 OSS SPIE Wind Connect was awarded […]

Stylish curve

UVDB Logo BMA Trade Logo