Hornsea 2 OWF

Prysmian – Hornsea 2 Offshore Wind Farm – August 2021 to June 2022 – 66kV Array & OSS Cables

Correll was delighted that Prysmian approached our organisation to take over the Termination and Testing contract on Hornsea 2. The Hornsea 2 project is being managed by our UK team based at our HQ depot in Skelton, North-East England.

Scope of works included:

  • Pre-project meetings
  • Evaluate existing RAMS
  • Post Lay Testing (continuity, insulation resistance, Time Domain Reflectometry and Optical Time Domain Reflectometry).
  • On the offshore assets:
    • Stripping the array cables to expose the HV cores and FO cable
    • Complete the permanent hang-off
    • Route the HV and FO cable into the TP/WTGS
    • Cleat the HV cores from the hang-off to the GIS
    • Terminate and splice the FO cable into the cabinet
    • Terminate three power cores into the GIS
    • Complete post installation testing from the onshore substation to the offshore assets (IR, TDR & OTDR)
    • Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone.

Download

For further information: Contact Us

More Projects from SPIE Wind Connect

Siemens - Framework Agreement (APAC)

Siemens – High Voltage Management (HV-M) Framework Agreement – December 2025 to Present – HV Services including Electrical Management Systems – APAC This framework agreement demands engineers who are not […]

Baltyk II & III OWF

Seaway 7 – Baltyk II and Baltyk III OWF – February 2026 to Present – Termination & Testing of 66kV inter-array cables (Poland) SPIE Wind Connect, has been awarded a […]

Dogger Bank C OWF

Deme – Dogger Bank C OWF – November 2025 to Present – Termination & Testing of 66kV inter-array cables Under this agreement, SPIE Wind Connect will carry out 66kV inter-array […]

Stylish curve

UVDB Logo BMA Trade Logo