Nordergrunde OWF

Senvion – Nordergrunde OWF – October 2016 to February 2017

Correll HV-M was contracted to CWind to provide termination, testing and commissioning activities on Senvion owned assets on the Nordegrunde OWF.  Correll engaged a project team of 8 specialist jointers, testers and commissioning engineers to perform the following activities:

  • Pre-projects meetings
  • Pre-projects Documentation, Procedures and RAMS
  • Cable terminations on the 33Kv transformer, NKT CB 36-630
  • Continuity, VLF and PD testing on the offline 33KV switchgear to transformer cable
  • Secondary injection testing on the REF 630 relay system for the CT commissioning
  • Commissioning works on the ABB ZX0.2 Switchgear & Switching activities
  • Issue ITS as part of client request and payment milestones.

For further information contact Will Sharrock, Business Lead, HV-Management: willsharrock@correllservices.com

 

More Projects from SPIE Wind Connect

Siemens - Framework Agreement (APAC)

Siemens – High Voltage Management (HV-M) Framework Agreement – December 2025 to Present – HV Services including Electrical Management Systems – APAC This framework agreement demands engineers who are not […]

Baltyk II & III OWF

Seaway 7 – Baltyk II and Baltyk III OWF – February 2026 to Present – Termination & Testing of 66kV inter-array cables (Poland) SPIE Wind Connect, has been awarded a […]

Dogger Bank C OWF

Deme – Dogger Bank C OWF – November 2025 to Present – Termination & Testing of 66kV inter-array cables Under this agreement, SPIE Wind Connect will carry out 66kV inter-array […]

Stylish curve

UVDB Logo BMA Trade Logo