Kriegers Flak OWF

Global Offshore – Kreigers Flak Cable Repair OWF (Denmark) – October 2020 to February 2022 – Array Termination and Testing

Global Offshore approached Correll Electrical Engineering (CEE) to support them with the HV and FO services associated with the Kreigers Flak cable repair/replacement project.

CEE were responsible for the Termination & Testing of the IAG cables between Wind Turbine Generators, including:

  • Mobilising 20 Technicians and 2 Offshore Installation Manager
  • Pre-project meetings
  • Site visits
  • Creation of RAMS
  • Creation of quality documentation
  • Project HIRA meetings
  • Post Lay Testing (continuity, insulation resistance, Time Domain Reflectometry and Optical Time Domain Reflectometry).

On the offshore assets:

  • Cutting of existing array cables ready for extraction
  • Stripping the array cables to expose the HV cores and FO cable
  • Complete the permanent hang-off
  • Route the HV and FO cable into the OSS/WTGS
  • Cleat the HV cores from the hang off to the GIS
  • Terminate and splice the FO cable into the cabinet
  • Terminate power cores into the GIS
  • Deliver an Inspection and Test Plan for the installed and tested system, forming part of key payment milestone.

More Projects from SPIE Wind Connect

Siemens - Framework Agreement (APAC)

Siemens – High Voltage Management (HV-M) Framework Agreement – December 2025 to Present – HV Services including Electrical Management Systems – APAC This framework agreement demands engineers who are not […]

Baltyk II & III OWF

Seaway 7 – Baltyk II and Baltyk III OWF – February 2026 to Present – Termination & Testing of 66kV inter-array cables (Poland) SPIE Wind Connect, has been awarded a […]

Dogger Bank C OWF

Deme – Dogger Bank C OWF – November 2025 to Present – Termination & Testing of 66kV inter-array cables Under this agreement, SPIE Wind Connect will carry out 66kV inter-array […]

Stylish curve

UVDB Logo BMA Trade Logo