18th March 2021

Orkney Islands

Global Marine Systems – Orkney Islands – May 2018 – June 2018 – 1 Subsea to Land Cable 

Correll Services was contracted by Global Marine Systems to complete cable jointing and testing works on subsea cables between island’s in Orkney.  Works included: 

  • Fabrication of project RAM’s 
  • Conducting project meetings 
  • Post load out testing,  
    • Time Domain Reflectometry (open & closed) 
    • Optical Time Domain Reflectometry (Unidirectional) 
    • Setup of Fibre Optical monitoring system within the carousel 
  • Post Lay Testing 
    • Time Domain Reflectometry (open & closed) 
    • Optical Time Domain Reflectometry  
  • HV/FO Jointing subsea cables to onshore land cable 
  • Completion of ITP documentation for issue to the client 

More Projects from SPIE Wind Connect

Siemens - Framework Agreement (APAC)

Siemens – High Voltage Management (HV-M) Framework Agreement – December 2025 to Present – HV Services including Electrical Management Systems – APAC This framework agreement demands engineers who are not […]

Baltyk II & III OWF

Seaway 7 – Baltyk II and Baltyk III OWF – February 2026 to Present – Termination & Testing of 66kV inter-array cables (Poland) SPIE Wind Connect, has been awarded a […]

Dogger Bank C OWF

Deme – Dogger Bank C OWF – November 2025 to Present – Termination & Testing of 66kV inter-array cables Under this agreement, SPIE Wind Connect will carry out 66kV inter-array […]

Stylish curve

UVDB Logo BMA Trade Logo