Centrica Platform 3B

Fabricom Quanta  Centrica Platform 3B – October 2020 to May 2021 – Cable Pulling Platform Cables  

CS were approached to support Quanta them with cable pull in activities of HV & LV cables on the platform between Transformers, Switch Gears etc. CS were responsible for the following,  

  • Pre-project meetings 
  • Site visits  
  • Creations of associated documentation 
  • Project HIRA meetings 
  • Mobilisation of PPE & tools via a 10ft container 
  • On the 2 x offshore platforms assets: 
    • Implement lift and pull plans 
    • OSS mobilisation and preparation 
    • Pull the HV cable to the associated assets  
    • Route the HV/LV cable to the associated assets  
    • Cleat the HV/LV cables to the associated assets 
    • Deliver an Inspection and Test Plan of the installed and tested system, forming part of key payment milestone. 

More Projects from SPIE Wind Connect

Siemens - Framework Agreement (APAC)

Siemens – High Voltage Management (HV-M) Framework Agreement – December 2025 to Present – HV Services including Electrical Management Systems – APAC This framework agreement demands engineers who are not […]

Baltyk II & III OWF

Seaway 7 – Baltyk II and Baltyk III OWF – February 2026 to Present – Termination & Testing of 66kV inter-array cables (Poland) SPIE Wind Connect, has been awarded a […]

Dogger Bank C OWF

Deme – Dogger Bank C OWF – November 2025 to Present – Termination & Testing of 66kV inter-array cables Under this agreement, SPIE Wind Connect will carry out 66kV inter-array […]

Stylish curve

UVDB Logo BMA Trade Logo