Carrera Pinto Solar Park

Wirescan – Carrera Pinto Solar Park – June 2023

Correll Group, High Voltage Management Division was approached by Wirescan, the pioneer of Wirescan Digital, a cable condition monitoring software following our previous installation works at London Array Offshore Wind Farm.

Works consisted of the installation of the cable monitoring sensors at all outgoing circuit feeders on the Carrera Pinto Solar Park located in Chile, SA.

The objective was to attain cable monitoring data that can be reviewed during site operations.

Schedule of works:

  • Review site documentation such at single line diagrams and installation procedures
  •  Mobilise one specialist HV Technician to Chile
  • Pre-project meetings
  • Installation of the cable monitoring sensors
  • Support the client when required for the commissioning works.

Download

For further information: Contact Us

More Projects from SPIE Wind Connect

Siemens - Framework Agreement (APAC)

Siemens – High Voltage Management (HV-M) Framework Agreement – December 2025 to Present – HV Services including Electrical Management Systems – APAC This framework agreement demands engineers who are not […]

Baltyk II & III OWF

Seaway 7 – Baltyk II and Baltyk III OWF – February 2026 to Present – Termination & Testing of 66kV inter-array cables (Poland) SPIE Wind Connect, has been awarded a […]

Dogger Bank C OWF

Deme – Dogger Bank C OWF – November 2025 to Present – Termination & Testing of 66kV inter-array cables Under this agreement, SPIE Wind Connect will carry out 66kV inter-array […]

Stylish curve

UVDB Logo BMA Trade Logo