BACK TO PROJECTS

16th March 2021

Burbo Bank OWF

Briggs Marine – Burbo Bank OWF Export Cable – April 2019 

Correll Services was contacted and mobilised at very short notice to fault find on a subsea export cable.  Utilising four HV/FO testing technicians working from each end of the cable, we successfully located the fault 20-25 metres outside the onshore substation.  We completed the fault–finding process using the following equipment: 

  • Bridge tester (HVB10) 
  • Surge Tester (Thumper) 
  • Optical Time Domain Reflectometry (OTDR) 

More Projects from SPIE Wind Connect

Siemens - Framework Agreement (APAC)

Siemens – High Voltage Management (HV-M) Framework Agreement – December 2025 to Present – HV Services including Electrical Management Systems – APAC This framework agreement demands engineers who are not […]

Baltyk II & III OWF

Seaway 7 – Baltyk II and Baltyk III OWF – February 2026 to Present – Termination & Testing of 66kV inter-array cables (Poland) SPIE Wind Connect, has been awarded a […]

Dogger Bank C OWF

Deme – Dogger Bank C OWF – November 2025 to Present – Termination & Testing of 66kV inter-array cables Under this agreement, SPIE Wind Connect will carry out 66kV inter-array […]

Stylish curve

UVDB Logo BMA Trade Logo