Jan De Nul – Thor OWF – August 2025 to Present – Termination & Testing of 66kV inter- cables – 72 WTGs, 16 Strings, 1 OSS
SPIE Wind Connect was awarded the contract by Jan De Nul, a global leader in maritime construction. The project is to complete the 66kV (IAC) termination and testing on 72 wind turbine generators for RWE’s Thor Offshore Wind Farm.
These works are due to commence in July 2025 with the mock-up scheduled for November 2024.
Jan De Nul was awarded the EPCI cable contracts by RWE in consortium with Hellenic Cables, and will provide the entire cable package, including the manufacture and installation of 60 kilometres of export cables on the 30-kilometre-long cable route from the offshore wind farm to shore, and approximately 200 kilometres of inter-array cables.
Offshore installation and commissioning of the cable system are expected in 2025.
Scope of work (but not limited to} the following elements:
For further information: Contact Us